Gas-fired cogeneration power station in Germany replaced turbine drain valves to reduce steam and energy losses.
During turbine start-up, drain valves must be open to ensure large quantities of condensate generated during warm-up are removed quickly, ensuring rapid start-up to meet demand and avoid damage. This application requires reliable and robust severe service valves to discharge flashing water at high pressures, and then when closed to have a tight shut-off.
Any steam passing through the turbine drain valves once closed (leakage) will have an impact on the efficiency of the turbine. An energy and power Generation company was experiencing leaks as a result of drain valve trim and seat erosiong
This was increasing maintenance time and costs to replace spare parts. The leaks meant the customer was losing 'high value' steam and energy from their turbine which was impacting the vacuum of the condenser downstream.
After walking the plant GESTRA recommended replacing the existing turbine drain valves with GESTRA's ZK 313 as a drain and warm-up valve solution; this would avoid leaks and steam losses, save energy and ensure the vacuum of the condenser downstream was not being affected.
The ZK 313 drain valve was able to operate reliably in this severe service drain application, ensuring efficient drainage at start-up followed by highly effective tight shut-off once the system was up-and-running. The ZK 313 has been operating reliably during repeated start-up cycles, giving the customer peace-of-mind due to reduced maintenance time and costs, as well as continuity of power supply generation.